DataCenter.forum
MARKET INTELLIGENCE

Wisconsin data-center projects.

3 source-linked project records currently in the canonical dataset, with 0 MW of published capacity represented where a project-level figure is available.

PROJECTS

Wisconsin buildout

Under construction

Beaver Dam Data Center

Meta · Beaver Dam, Wisconsin

Meta's AI-optimized Beaver Dam campus spans more than 700,000 square feet and represents an investment of more than $1 billion.

CapacityNot published
Investment$1B+
CheckedSep 30, 2026
Open record →
Operational / expanding

Fairwater / Mount Pleasant Datacenter Campus

Microsoft · Mount Pleasant, Wisconsin

Microsoft's first Mount Pleasant facility is fully operational, with the company continuing a multi-year hyperscale construction program in Southeast Wisconsin.

CapacityNot published
Investment$4.7B local spend est. 2024–2028
CheckedSep 30, 2026
Open record →
Announced / development

Stargate Wisconsin

OpenAI / Oracle / Vantage · Wisconsin

The Midwest Stargate site announced in September 2025 was later identified by OpenAI as a Wisconsin project developed by Oracle in partnership with Vantage.

CapacityNot published
InvestmentNot published
CheckedSep 30, 2026
Open record →